Project Status For:, Abim TC

Project Description

The scope of works involves furnishing the necessary labour, materials, equipment and services for the construction of Abim town water supply system and consists of the following main elements: Construction of 2 No. pump stations inclusive of perimeter fencing and auxiliary site works; supply, installation and commissioning of 2 No. Submersible pumps with discharges of 23m3/hr and 6m3/hr at heads of 92m and 143m respectively including all associated accessories, powered by the UECDL grid and a standby 30kVA diesel generator; supply, laying and commissioning of 5.1km of OD 160mm, OD 110mm and OD 63mm PN 16 transmission mains; supply, laying and commissioning of 20.4km of OD 110mm &OD 160mm uPVC and OD 32mm-OD 90mm HDPE PN 6 distribution pipe lines inclusive of all associated fittings and ancillaries; supply, installation and commissioning of a 175m3-capacity cold pressed panel steel storage tank raised on a 1.2m dwarf wall inclusive of all fittings and auxiliary site works; construction of a Water Office inclusive of auxiliary site works & perimeter fencing and furnishing it with basic furniture and IT equipment; construction of a Chlorine Dosing Unit fully equipped with an Electrolytic Disinfection Machine and its accessories; and making of 150 private service connections and 3 public stand posts

Project Timing

  • Start Date: 13-12-2011
  • Predicted End: 03-10-2014

Current Tasks

The system was technically commissioned on 2nd April 2014

Current Holds

Defects Liability Period: From 10th March 2014 to 9th March 2015

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator