Project Status For:, Barr

Project Description

Name of town/RGC Barr
Project Name Feasibility studies and detailed Engineering design of water supply and sewerage system.
Contract #. LIRA531/SRVCS/11-12/00024
Population
Scope of contract Inception report. Feasibility study report (Socio-economics, hydro-geological, engineering reports). Final design report (detailed designs, BoQ, Drawings, tender documents)
Revised Contract Price UGX 159,210,000
Contractor Warner Consults Ltd
Supervisor WSDF-N
Date of commencement 19th February 2013
Planned date for completion  20th January 2015
Actual Progress (%) 80%
Remarks This contract has been delayed by well drilling programme for ground water resources to be analysed. The Consultant has been instructed to re-orient the design considering extension of water from Lira Town system under NW&SC.

Project Timing

  • Start Date: 02-19-2013
  • Predicted End: 01-20-2015

Current Tasks

Current Holds

This contract has been delayed by well drilling programme for ground water resources to be analysed

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator