Project Status For:, Dokolo

Project Description

Name of town/RGC Dokolo
Project Name Design Review and Construction Supervision for piped water supply and sanitation facilities.
Contract #. MWE/WSDF-N/SRVCS/12-13/00017
Population
Scope of contract Design review. Construction supervision. Timely briefs and reports on progress. Note: For each report, the consultant will deliver four (4) copies and electronic/soft copies (both MS, adobe Acrobat and other relevant software) on a CD.
Revised Contract Price UGX 368,875,000/=
Contractor M/S Kagga and Partners Consulting Engineers.
Supervisor WSDF-N
Date of commencement 2nd December 2014
Planned date for completion  15th January, 2016.
Actual Progress (%) 0%
Remarks The consultancy contract duration includes for defects period monitoring of works contract. The highest duration of works contract in this consultancy is 12months, making the service contract duration to be 24months inclusive of defects period There were delays in starting the Dokolo TC construction works, however, the procurement is now nearing completion. The project for Ibuje is at 85% completion.

Project Timing

  • Start Date: 12-02-2014
  • Predicted End: 01-15-2016

Current Tasks

Current Holds

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator