Project Status For:, Ibuje

Project Description

 ibuje-plant
Name of town/RGC Ibuje
Project Name Ibuje RGC Water Supply and Sanitation System
Contract #. MWE/WSDF-N/WRKS/12-13/00026
Population 6,721
Scope of contract Two (2) production wells yielding 7m³/hr. (DWD 31175, Ginnery Aketo,) and DWD 31178 Miciri 8m³/hr. to be fitted with submersible pump. 02 pump and generator houses with guard houses. 01 office block. 4000m of OD75mm HDPE PN16 transmissions mains from sources 1 and 2 to Reservoir tank. 10km of distribution mains(1500m OD110mm, 2000m OD90mm, 2500m OD75mm, 4000m OD63, all to PN10 HDPE). 01-04 Stance water bond public toilet. 01 Reservoir tanks of 100m³. Water kiosks (2No.). Service connections (200 No.). Support to institutional sanitation (2No. @ 5Stance) and construction of house hold ECOSAN toilets (7No.) for demonstration purposes. Catchment protection at the sources. Grid Power connection to both sources as main source and Perkins Engine Generator as standby source. Supply of tools and equipment for operation and maintenance.
Revised Contract Price UGX: 1,585,919,049/=, original 6 Months. Extension 2 months
Contractor Balaji Industrial and Agricultural Castings
Supervisor Kagga and Partners/WSDF-N
Date of commencement 15th January 2014
Planned date for completion 15th July, 2014. Proposed extension; 30th September, 2014.
Actual Progress (%) 85%
Remarks The works are expected to be substantially complete by 30th September, 2014, however delays will be experienced due to shipment of reservoir tank whose specifications were changed coupled with low response by communities for connections ,test-running will be conducted during the defects liability period in the presence of the operator.

Project Timing

  • Start Date: 10-01-2013
  • Predicted End: 04-01-2014

Current Tasks

Current Holds

The works are expected to be substantially complete by 30th September, 2014, however delays will be experienced due to shipment of reservoir tank whose specifications were changed coupled with low response by communities for connections ,test-running will be conducted during the defects liability period in the presence of the operator.

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator