Project Status For:, Moyo

Project Description

Name of town/RGC Moyo
Project Name Feasibility studies and detailed Engineering design of water supply and sewerage system.
Contract #. MOYO539/SRVCS/11-12/00041
Population
Scope of contract Inception report. Feasibility study report (Socio-economics, hydro-geological, engineering reports). Final design report (detailed designs, BoQ, Drawings, tender documents)
Revised Contract Price UGX 233,500,000
Contractor Techno Consults Ltd
Supervisor WSDF-N
Date of commencement 27th February 2013
Planned date for completion 27th September 2013, extended to 15th June, 2014 by contracts committee approval
Actual Progress (%) 100%
Remarks Final design report submitted by the consultant after recasting recommendations during presentation. The report is now under review before presentation to design review committee for approval.

Project Timing

  • Start Date: 02-19-2013
  • Predicted End: 01-20-2015

Current Tasks

The report is now under review before presentation to design review committee for approval.

Current Holds

The report is now under review before presentation to design review committee for approval.

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator