Project Status For:, Ngetta

Project Description

Name of town/RGC Ngetta
Project Name Laying HDPE pipes at Ngetta
Contract #. MWE/WSDF-N/WRKS/12-13/00023
Scope of contract
  1. General site clearance, Laying of 4200m of HDPE Transmissions mains from booster pump house to 10m3Reservoir tank,
  2. HDPE Reservoir tank on steel tower of 10m³ capacity at Leo Atubo S.S.S
  3. Laying of 1000m of OD 50mm HDPE distribution line
  4. Extension of three phase power line and connection to the pump house.
  5. Supply and installation of 3-phase pumps inclusive of all control panel and accessories.
  • Expansion of the pump house to accommodate the 3 phase pumps
  • Pipes and couplers supplied and delivered in Lira by MWE.
  • Three phase pumps supplied and installed under a framework contract by the Ministry.
Revised Contract Price UGX 97,300,000
Contractor Kheny Technical Services Ltd
Date of commencement 21st October 2013
Planned date for completion 21st December 2013
Actual Progress (%) 100%
Remarks Completed and handed over to NWSC for management, but still under defects liability period.

Project Timing

  • Start Date: 10-01-2013
  • Predicted End: 04-01-2014

Current Tasks

Still under defects liability period.

Current Holds

Completed and handed over to NWSC for management, but still under defects liability period.

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator