Project Status For:, Ovujo

Project Description

ovugo-water-tank ovugo-plant
Project Name Ovujo RGC Piped Water Supply and Sanitation System
Contract # MWE/WSDF-N/WRKS/12-13/00027
Population 31,055
Scope of contract 02 pump houses at 02 pump stations. 01 office block. 8200m of OD90mm HDPE PN16 transmissions mains from sources 1 and 2 to Reservoir tank. 11km of distribution mains(2500m OD110mm, 2000m OD90mm, 2500m OD75mm, 4000m OD63, all to PN10 HDPE). 1No @4Stance water-bond public toilet. 01 Reservoir tank of 100m³ capacity. Water kiosks (2No.). Service connections (200 No.). Support to institutional sanitation (2No. @ 5Stance) and construction of house hold ECOSAN toilets (7No.) for demonstration purposes.Catchment protection at the sources. Installation of Perkins Engine Generator as main source.Supply of tools and equipment for operation and maintenance. Chlorination Unit.02 production well yielding 9.0m³/hr and 20.0m3/hr to be fitted with submersible pumps.
Revised Contract Price UGX: 1,263,734,110/=
Contractor M/S NORM CONTRAS LTD
Supervisor JOADAH CONSULTS LTD/WSDF-N
Date of commencement 15th January 2014
Planned date for completion 15th July, 2014. Extension; 30thSeptember, 2014.
Actual Progress (%) 90%
Remarks The works are expected to be substantially complete and ready for hand over by 30th September, 2014. A test-running period will be conducted by the contractor in the presence of the operator. Defects period will run for 12 months

Project Timing

  • Start Date:
  • Predicted End:

Current Tasks

Current Holds

A test-running period will be conducted by the contractor in the presence of the operator. Defects period will run for 12 months

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator