Project Status For:, Paidha

Project Description

paidha-water-plant
Project Name Paidha town water supply and sanitation system
Contract # ZOMB587/WRKS/11-12/00001
Scope of contract 02 boreholes with submersible pumps (75 m3/h and 36 m3/h). ) 01 generator. 06.8-km transmission lines. 02-200-m3 reservoir tanks. 30-km of OD 110/63/50 mm HDPE distribution network. 963 service connection. 04 water kiosk. 02-8-stances water bond public toilets. 01 office block. National grid extension to the 02 pumps stations.
Revised Contract Price UGX 3,457,357,145
Contractor PALM CONSTRUCTION Ltd.
Date of commencement 15th January 2013
Planned date for completion Originally 15th January, 2014. Extended to 31st May 2014
Actual Progress (%) 100%
Remarks The piped water supply system and sanitation project has been scheduled for technical commissioning on 6th October, 2014, daily operations has already been handed over to NW&SC to manage on behalf of the local authorities, but still remain under the defects liability.

Project Timing

  • Start Date: 01-15-2013
  • Predicted End: 05-13-2014

Current Tasks

Current Holds

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator