Project Status For:, Patongo TC

Project Description

 patongo-tc-fac
Name of town/RGC Patongo TC
Project Name Patongo TC Piped Water Supply and Sanitation System
Contract #. MWE/WSDF-N/WRKS/12-13/00030
Population 26,557
Scope of contract Two (2) production wells yielding 31m³/h (DWD 31165) and DWD 31166 5m³/h to be fitted with submersible pumps. 02 pump and generator houses with guard houses. 01 office block. 1800m of OD110mm and 1700m OD63mm HDPE PN16 transmissions mains from sources 1 and 2 to Reservoir tank. 17km of distribution mains(2500m OD110mm, 2500m OD90mm, 4000m OD75mm, 8000m OD63, all to PN10 HDPE). 01-08 Stance water bond public toilet. 1No. Reservoir tank of 200m³. Water kiosks (4No.) Service connections (600 No.). Support to institutional sanitation (2No. @ 5Stance) and construction of house hold ECOSAN toilets (7No.) for demonstration purposes. Catchment protection at the sources. Grid Power connection to both sources as main source and Perkins Engine Generator as standby source. Supply of tools and equipment for operation and maintenance. Chlorination Unit.
Revised Contract Price UGX: 2,092,169,521/=, 8 Months.
Contractor PALM CONSTRUCTION LTD
Supervisor ILISO CONSULTING LTD/WSDF-N
Date of commencement 15th January 2014
Planned date for completion 15thNovember, 2014
Actual Progress (%) 70%
Remarks Contract duration extended up to 15th November, 2014. The main pending works are on reservoir tank, service connections and Construction of institutional toilet has delayed due to bad weather and the design has been changed to Ecosan.

Project Timing

  • Start Date: 10-01-2013
  • Predicted End: 04-01-2014

Current Tasks

Current Holds

The main pending works are on reservoir tank, service connections and Construction of institutional toilet has delayed due to bad weather and the design has been changed to Ecosan

Project Overview and Overall Progress

20% 20% Advocacy meetings

Awareness Creation at District and Sub County Levels Call for Applications for detailed designs Receiving and Verifying applications

40% 40%Design and Mobilization

Procurement of consultants for Mobilization and design Mobilization, Feasibility Studies, Baseline Surveys Design Documentation and Preparation of Tender Documents

60% 60%Fulfillment of Community Obligations

Land acquisition, cash contributions

80% 80%Construction and O&M Set Up

Procurement of Contractors and Consultants Construction of WSS Facilities Fulfillment of the Sanitation Programme Selection and Training of Private Scheme Operator